Por favor, use este identificador para citar o enlazar este ítem: http://dspace.espoch.edu.ec/handle/123456789/7219
Registro completo de metadatos
Campo DC Valor Lengua/Idioma
dc.contributor.advisorOrozco Pérez, Angel Alberto-
dc.contributor.authorVillacís Bonilla, Milton Eliecer-
dc.date.accessioned2017-09-08T15:17:39Z-
dc.date.available2017-09-08T15:17:39Z-
dc.date.issued2017-07-
dc.identifier.citationVillacís Bonilla, Milton Eliecer. (2017). Optimización del mantenimiento planificado (PMO) de la Central de generación eléctrica Cuyabeno Bloque 58. Escuela Superior Politécnica de Chimborazo. Riobamba.es_ES
dc.identifier.urihttp://dspace.espoch.edu.ec/handle/123456789/7219-
dc.descriptionSe realizó la optimización de las tareas de mantenimiento planificado de la Central de Generación Eléctrica Cuyabeno, conformada por siete grupos electrógenos a diésel, con la finalidad de tener una mayor disponibilidad de los mismos, disminuyendo el número de paradas imprevistas ante fallas en los equipos. Para ello, se realizó un diagnóstico de la situación actual, analizando las tareas existentes y los modos, efectos de falla y sus consecuencias, se utilizó como guía los nueve pasos de la metodología Optimización del Mantenimiento Planificado (PMO), se utilizaron datos tanto físicos, como digitales, así como también se tomaron sugerencias del personal de operaciones y mantenimiento. La ejecución de este trabajo ha generado los siguientes resultados: 36% menos en el costo de mantenimiento por cada barril de petróleo producido, una mejora en la disponibilidad operativa del 3.71% y una reducción de las pérdidas de producción inicial del 14% del año 2014 al 2015 y del 36% del año 2015 al 2016, esto se ha logrado con la implementación de nuevas tareas y la optimización de las existentes, mejorando los índices de mantenimiento, reduciendo el número de fallas funcionales, optimizando recursos, generando la participación del personal de operaciones en actividades de mantenimiento autónomo. Todas las tareas han sido ingresadas al sistema de gestión de mantenimiento para su ejecución. Se concluye que la aplicación de la metodología PMO es efectiva en equipos con alto índice de fallas. Se recomienda la revisión continua de los planes y programas de mantenimiento en la central de generación Cuyabeno.es_ES
dc.description.abstractThe planned maintenance tasks of the Cuyabeno Electric Generation Plant, made up of seven diesel generators, were optimized in order to have a greater availability of them, reducing the number of unexpected shutdowns due to failures in the equipment. With this purpose, a diagnosis of the current situation was performed. It analyzed the current tasks and modes, failure effects and their consequences, the nine steps of the Optimized Maintenance Planning (PMO) methodology were used as a guide, both physical data, as digital, as well as suggestions from operations and maintenance personnel. The execution of this work has generated the following results: 36% less maintenance costs per barrel of oil produced, an improvement in the operational availability of 3.71% and a reduction of the initial production losses of 14% in 2014 To 2015 and 36% from 2015 to 2016. These results have been achieved with the implementation of new tasks and the optimization of existing ones, improving maintenance rates, reducing the number of functional failures, optimizing resources and, generating staff participation of operations in autonomous maintenance activities. All tasks have been entered into the maintenance management system for execution. It is concluded that the application of the PMO methodology is effective in equipment with high failure rate. As well as continuous review of maintenance plans and programs at the Cuyabeno Generation Plant is recommended.es_ES
dc.language.isospaes_ES
dc.publisherEscuela Superior Politécnica de Chimborazoes_ES
dc.relation.ispartofseriesUDCTIPEC;20T00870-
dc.rightsinfo:eu-repo/semantics/openAccesses_ES
dc.subjectTECNOLOGÍA Y CIENCIAS DE LA INGENIERÍAes_ES
dc.subjectINGENIERÍA EN MANTENIMIENTOes_ES
dc.subjectMANTENIMIENTO PLANIFICADOes_ES
dc.subjectCENTRAL DE GENERACIÓNes_ES
dc.subjectGESTIÓN DE ACTIVOSes_ES
dc.subjectOPTIMIZACIÓN DEL MANTENIMIENTO PLANIFICADO (PMO)es_ES
dc.subjectFALLAes_ES
dc.subjectCUYABENO (COMUNIDAD)es_ES
dc.titleOptimización del mantenimiento planificado (PMO) de la Central de generación eléctrica Cuyabeno Bloque 58es_ES
dc.typeinfo:eu-repo/semantics/masterThesises_ES
dc.contributor.miembrotribunalFreire Miranda, Jorge-
dc.contributor.miembrotribunalBautista Naranjo, Victor Rubén-
dc.rights.urihttps://creativecommons.org.//licenses/by-nc-sa/3.0/ec/es_ES
Aparece en las colecciones: Maestrias: Modalidad Proyectos de Investigación y Desarrollo

Ficheros en este ítem:
Fichero Descripción Tamaño Formato  
20T00870.pdf3,17 MBAdobe PDFVista previa
Visualizar/Abrir


Este ítem está sujeto a una licencia Creative Commons Licencia Creative Commons Creative Commons